Search Results:
Results

Project overview

Upgrading the equipment at PEC will increase its generating capacity by 50 MW to an output of
600 MW. The efficiency upgrades will be limited to replacing parts of the existing natural gas fired combustion turbines. All upgrade activities will take place within the existing facility and there will be no changes or expansion beyond the existing PEC footprint.
What’s being upgraded?
The efficiency upgrades will include replacing parts of the existing natural gas fired combustion turbines with parts that will allow increased electrical output. The work is similar to regular facility maintenance activities and will be confined to the existing facility footprint. There will be no changes or expansion beyond the existing PEC footprint.
Environmental screening process and project timeline
Since the project will result in a 50 MW increase in the electrical output of PEC, it is subject to the Environmental Screening Process for Electricity Projects subject to Ontario Regulation 116/01, under the Ontario Environmental Assessment Act. A Notice of Commencement of a Screening and Invitation to a Public Meeting was issued on September 6, 2023, to communicate the start of the Environmental Screening Process.

Request for exemption
Given that that proposed efficiency upgrades to PEC are minor – similar to routine maintenance activities – and contained entirely within the footprint of the existing facility, Atura Power is requesting that the Ontario Ministry of Environment, Conservation and Parks grant an exemption to the Ontario Environmental Assessment Act for this project.
We want to hear from you
Atura Power is committed to engaging with Indigenous communities, agencies, the public, and other interested parties on all our projects. We invite you to attend an upcoming virtual public meeting to learn more about the PEC efficiency upgrades and provide feedback.
How to join:
Date: October 5, 2023
Time: 6:30 to 7:30 p.m.
Participation link: Available October 5, 2023
Access for all is important, so please let us know if you have accommodation needs related to the virtual public meeting through the Contact us form below.
If you’re unable to participate, meeting materials will be posted here following the meeting.
Contact us
Comments and information regarding this project are being collected in accordance with the Freedom of Information and Protection of Privacy Act for the purpose of meeting environmental assessment requirements. With the exception of personal information, all comments received will become part of the project record.